The National Highways Authority of India (NHAI) has recorded a 56 per cent project completion rate across all phases of NHDP in 2007-08. The phase-wise details of actual achievement under the National Highways Development Project (NHDP) during 2007-08 are indicated as below:-
NHDP Phase
2007-08
Target (kms)
Achievement (kms)
NHDP Phase-I
Target (kms) - 437
213
NHDP Phase-II
Target (kms) - 2013
Achievement (kms) - 1020
NHDP Phase-III
Target (kms) - 435
Achievement (kms) - 381
NHDP Phase-V
Target (kms) - 0
Achievement (kms) - 0
Total
Target (kms) - 2885
Achievement (kms) - 1614
This information was given by the Minister of State for Shipping, Road Transport and Highways, Shri K.H. Muniyappa in a written reply in the Rajya Sabha today.